PVWC 2MG Verona Water Tank
PVWC 2MG Verona Water Tank
PVWC 2MG Verona Water Tank
PVWC 2MG Verona Water Tank
PVWC 2MG Verona Water Tank
PVWC 2MG Verona Water Tank
Passaic Valley Water Commission Contract 16-B-14
Rehabilitation, Repainting, Repair and Disinfection of the
2MG Verona Water Storage Tank No. 1
Duration of Project:
-
Work Started: April 2016
-
Wok Completed: July 2016
Steel Configuration
-
94'-00" diameter by 40'-00" tall 2MG water storage tank
Scope of Work
-
Abrasive blasting clean exterior to NACE No. 3/SSPC SP-6 (Commercial Blast) and interior to NACE No. 2/SSPC SP-10 (Near-White Blast) and the application of a Sherwin Williams high-performance coating system to both the interior and exterior, including a 30MIL epoxy lining
-
Miscellaneous concrete repairs
-
Miscellaneous steel repairs
-
Remove and replace vent pallet
-
Modify roof railing system
-
Remove and replace shell manhole gaskets and bolts
-
Furnish and install 18" duck bill check valve