NJ Turnpike Contract T100.321

Rehabilitation of Structure Nos. N6.49, N6.80E & N6.80W

Duration of Project:

  • Work Started: August 2017

  • Wok Completed: Anticipated Completion March 2020

Prime Contractor:

  • Creamer Sanzari, A Joint Venture

Scope of Work:

 

  • Installation of approximately 500,000 SF SafeSpan platform and Safway QuikDeck

  • Abrasive blasting cleaning to NACE No. 2/SSPC SP-10 (Near-White Blasting Cleaning) of approximately 1,000,000 SF structural steel and the application of an Organic Zinc Rich Epoxy Primer, Epoxy Intermediate and Aliphatic Urethane Finish (Prime Coat, Intermediate Stripe Coat, Intermediate Full Coat, Finish Coat).

  • Application of RPM Belgium substructure waterproofing membrane

  • Abatement and application of Slip-'B' zinc coating to hundreds of steel repairs over approximately 1-mile of the structure

  • Maintenance and protection of traffic over local roadways