top of page

NJ Turnpike Contract T100.275

Rehabilitation and Repainting N7.13 to N7.52

Jersey City

Duration of Project:

  • Work Started: March 2016

  • Wok Completed: Anticipated December 2016

 

Steel Configuration

  •  Approximately 300,000 sq. ft. of standard steel configurations (Girders, Diagraphms, Cross Members and Bearings)

 

Scope of Work

  • Abrasive blasting cleaning to NACE No. 2/SSPC SP-10 (Near-White Blasting Cleaning) and the application of an Organic Zinc Rich Epoxy Primer, Epoxy Intermediate and Aliphatic Urethane Finish (Prime Coat, Penetrating Sealer, Intermediate Stripe Coat, Intermediate Full Coat, Finish Coat). Work also included caulking of bearings

  • Installation of 200,000SF Safespan platform

  • Miscellaneous concrete repairs

  • Abrasive blast concrete and application of RPM Belgium Matacryl Machine 60MIL seamless waterproofing membrane

bottom of page