NJDOT Maintenance Bridge Painting Contract 2013-2

Routes 17, 4 and 208

Duration of Project:

  • Work Started: September 2013

  • Wok Completed: December 2015

 

Steel Configuration

  •  Approximately 500,000 sq. ft. of standard steel configurations (Girders, Diagraphms, Cross Members and Bearings)

 

Scope of Work

  • Abrasive blasting cleaning to NACE No. 2/SSPC SP-10 (Near-White Blasting Cleaning) and the application of an Organic Zinc Rich Epoxy Primer, Epoxy Intermediate and Aliphatic Urethane Finish (Prime Coat, Intermediate Stripe Coat, Intermediate Full Coat, Finish Coat). Work also included caulking of bearings and the application of waterproof membrane to concrete abutments and pier caps.

  • Miscellaneous concrete repairs

  • Miscellaneous steel repairs

 

Project Challenges

  • Coordinating with the NYCDOT, NJ Turnpike, PANYNJ and NJDOT to install 100,000 sq. ft. of platform on three structures over the NJ Turnpike